The stabilization of a slope-viaduct system without closing traffic

Risultato della ricerca: Paper

8 Citazioni (Scopus)

Abstract

ABSTRACT A case history concerned with the stabilisation of a slope-viaduct system is reported. The two-carriageway viaduct was built 39 years ago on a rather gentle slope that did not show any sign of instability. In 2010 a landslide took place and damaged the viaduct. As the relocation of the motorway was deemed unpracticable, the alternative solution of stabilising the slope and repairing the viaduct was chosen. The owner asked to design remedial measures that did not require the closure of the viaduct. This was possible since the movements of the slided mass were slow and regular. The slope-viaduct system was stabilised by improving, firstly, the bearing conditions of the decks, then strengthening the existing foundations of the involved piers, and finally stabilising the slope by reducing the pore water pressure by means of subhorizontal drains. The remedial works were successfully carried out and resulted to be effective.
Lingua originaleEnglish
Stato di pubblicazionePublished - 2015

All Science Journal Classification (ASJC) codes

  • Soil Science
  • Environmental Science(all)
  • Earth and Planetary Sciences(all)

Cita questo

@conference{ee3da9cd015140ed96944a11241dc723,
title = "The stabilization of a slope-viaduct system without closing traffic",
abstract = "ABSTRACT A case history concerned with the stabilisation of a slope-viaduct system is reported. The two-carriageway viaduct was built 39 years ago on a rather gentle slope that did not show any sign of instability. In 2010 a landslide took place and damaged the viaduct. As the relocation of the motorway was deemed unpracticable, the alternative solution of stabilising the slope and repairing the viaduct was chosen. The owner asked to design remedial measures that did not require the closure of the viaduct. This was possible since the movements of the slided mass were slow and regular. The slope-viaduct system was stabilised by improving, firstly, the bearing conditions of the decks, then strengthening the existing foundations of the involved piers, and finally stabilising the slope by reducing the pore water pressure by means of subhorizontal drains. The remedial works were successfully carried out and resulted to be effective.",
author = "Calogero Valore and Maurizio Ziccarelli",
year = "2015",
language = "English",

}

TY - CONF

T1 - The stabilization of a slope-viaduct system without closing traffic

AU - Valore, Calogero

AU - Ziccarelli, Maurizio

PY - 2015

Y1 - 2015

N2 - ABSTRACT A case history concerned with the stabilisation of a slope-viaduct system is reported. The two-carriageway viaduct was built 39 years ago on a rather gentle slope that did not show any sign of instability. In 2010 a landslide took place and damaged the viaduct. As the relocation of the motorway was deemed unpracticable, the alternative solution of stabilising the slope and repairing the viaduct was chosen. The owner asked to design remedial measures that did not require the closure of the viaduct. This was possible since the movements of the slided mass were slow and regular. The slope-viaduct system was stabilised by improving, firstly, the bearing conditions of the decks, then strengthening the existing foundations of the involved piers, and finally stabilising the slope by reducing the pore water pressure by means of subhorizontal drains. The remedial works were successfully carried out and resulted to be effective.

AB - ABSTRACT A case history concerned with the stabilisation of a slope-viaduct system is reported. The two-carriageway viaduct was built 39 years ago on a rather gentle slope that did not show any sign of instability. In 2010 a landslide took place and damaged the viaduct. As the relocation of the motorway was deemed unpracticable, the alternative solution of stabilising the slope and repairing the viaduct was chosen. The owner asked to design remedial measures that did not require the closure of the viaduct. This was possible since the movements of the slided mass were slow and regular. The slope-viaduct system was stabilised by improving, firstly, the bearing conditions of the decks, then strengthening the existing foundations of the involved piers, and finally stabilising the slope by reducing the pore water pressure by means of subhorizontal drains. The remedial works were successfully carried out and resulted to be effective.

UR - http://hdl.handle.net/10447/332703

UR - https://www.icevirtuallibrary.com/doi/abs/10.1680/ecsmge.60678.vol2.035

M3 - Paper